- Home
- Services
- City Improvement Projects
- Westminster in the Works
- Big Dry Creek Sewer Interceptor Project
Big Dry Creek Sewer Interceptor Project
What’s Happening Now
The City of Westminster is planning to upgrade a major sewer pipeline located within the Big Dry Creek corridor. Periodic fieldwork will be conducted in 2026 within the Big Dry Creek Open Space adjacent to the existing pipeline and near portions of the trail between Harmony Parkway and Huron Street, north of 128th Avenue.
Schedule
The project will take place in phases:
- Winter 2026: Evaluation and design
- 2027: Anticipated start of construction
More detailed schedules and trail information will be shared in advance of construction, including notice of expected detours or temporary closures.
Crews will conduct geotechnical drilling, sampling, surveying, inspections, and pipe cleaning. Heavy equipment will be used at times. Trail users and visitors are encouraged to use caution, adhere to signage, and avoid active work areas when using the open space trail.
What Neighbors and Trail Users Can Expect
The City recognizes that this work is taking place in an area valued by residents and trail users. Construction planning will carefully consider open space use, nearby residences, and environmental protections. During the project, the City will focus on:
- Maintaining trail access whenever it is safe to do so
- Using short-term, clearly marked detours if temporary closures are needed
- Restoring disturbed areas once work is complete
- Managing noise, odors, and construction activity to minimize impacts
Future Work Planned
The project focuses on evaluating and improving a large underground sewer line located near Big Dry Creek, adjacent to open space and multi-use trails. Planned work will generally include:
- Inspection and evaluation of the existing underground pipeline
- Design of a solution that strengthens or extends the life of the pipeline, minimizing replacement where feasible
- Targeted construction activities to improve long-term reliability
- Temporary access areas for crews and equipment, coordinated to reduce disruption
Although the pipeline is buried deep below the ground, accessing it requires surface activity at select locations. These are activities will be planned to limit the overall footprint and duration of impacts to nearby homes, open space, and recreational areas.
-
Big Dry Creek Sewer Interceptor Project
Phone: 720-442-8149
About the Project
Within the Big Dry Creek corridor is a major buried sewer pipeline — called an interceptor sewer — that plays a critical role in safely conveying wastewater from homes and businesses to the Big Dry Creek Wastewater Treatment Facility.
This project is part of the City of Westminster’s long-term effort to maintain reliable and safe wastewater service. Portions of this infrastructure were installed in the 1970s. Proactively evaluating and improving aging infrastructure helps reduce the risk of failures, mitigate emergency repairs, protect water quality in Big Dry Creek, and support the system to continuously serve the community well into the future.
The City is committed to completing this work in a manner that protects nearby neighborhoods, preserves open space, and maintains trail access whenever possible.
The City is committed to keeping neighbors and trail users informed throughout the project. Project updates will be posted on this page and shared through City communication channels. Informational signage will also be posted along affected trail segments.
This project represents an essential investment in Westminster’s infrastructure — and in protecting the natural and recreational spaces along the Big Dry Creek corridor as a valued asset of the community.
Stay informed about the project's progress and receive construction updates by signing up below for email notifications.